Mountain Times Home Updated Every Thursday Evening

March 12, 2009 EDITION
spacer
newscommunityentertainmentcalendarmarketplacevisitors guidesabout usclassifieds
spacer



corneround
spacer textsizeplusminusPrint Friendly 

Bridging Parkway Delays
Goshen Creek project will continue through spring amid complaints from area businesses

Spring travelers along the Blue Ridge Parkway will face continued detours around Boone and Blowing Rock.


The rebuilding of the Goshen Creek Bridge on the Blue Ridge Parkway began in early 2008. File photo
The Goshen Creek Bridge between the Aho and Bamboo areas outside of Boone on the parkway is still undergoing repairs, with the completion date already well past and work still under way.

Larry Hultquist, an engineer with the Blue Ridge Parkway office in Asheville, said the project, which began in early 2008, had been delayed because of weather and changes to the structural design of the bridge decking and rails.

“One of the reasons it has been delayed is because of a bad winter,” Hultquist said. “We also had to change the plans because of what contractors found when they were working on the project. We’ve had to recast the concrete, do a redesign, finish the concrete deck and put up new railing.”

Hultquist said the project had led to concern among local businesses because of the effect on tourism. He said some business owners had called the Blue Ridge Parkway office to complain about the extended closure, with more than six miles of the parkway closed.

“We know it’s been a heartache for people up there,” Hultquist said. “We didn’t intend for this to take so long. We have heard indirectly from some commercial establishments that it’s affecting their businesses in Boone.”
Hultquist said the new workload was important because of safety concerns. The previous guard rails didn’t meet national highway safety standards, and the concrete for the decking must stand up to decades of travel. The previous asphalt decking had complete cracks in it that allowed visibility all the way through.

The bridge was built in 1948, and, before any repair work begun, it was extensively recorded and documented by the National Park Service and North Carolina State Historic Preservation.

These records will be stored in the archives of the Blue Ridge Parkway, North Carolina Division of Archives and History/State Historic Preservation Office and the Eastern Federal Land Highway Division office in Sterling, Va.

The good news for history buffs and those with a sense of nostalgia for the unique stone bridge is the overall character of the structure was retained.

“We’ve already done all of the stone work we’re going to be doing,” Hultquist said. “It has some huge beautiful granite stones, so we did point work, redid all the joints and repaired some of the stone from the ground up.

The stonework above the bridge deck was left undisturbed, though the asphalt covering of the bridge bed will now be concrete. The picket styles were also changed, but the rock columns plunging nearly 100 feet will still retain their unique visual impact.

“When you replace a deck on a bridge it has to be done right,” Hultquist said. “It’s a safety issue, and this contractor has been slow.”

The project was awarded at $2.68 million, which was $120,000 below project estimates to Taylor & Murphy Construction Company of Asheville.

The project was supposed to have been completed by Dec. 15, but weather delays and a project redesign have now pushed the project and associated road closing to the beginning of summer. The contractor and park service also had to renegotiate because of changes to the project, which further created delays.

The detour between U.S. 321 and the Bamboo section will likely remain in place until the project’s new completion date of June 1.

The detour for visitors traveling south begins at milepost 285.5 in Bamboo Gap. Those visitors follow state road (SR) 1514 Bamboo Road to Deerfield Road, following the detour signs along U.S. 321 south of Boone and connecting back to the parkway at milepost 291.8.

Parkway visitors traveling north begin the detour at milepost 291.8, the intersection of U.S. 321, following the detour signs along U.S. 321 to SR 1514, Deerfield Road to Bamboo Road, which will bring them back to the parkway at milepost 285.5.

More information about the project, including archival photographs, can be found at www.virtualblueridge.com/parkway/history/goshen-creek-bridge.asp.




To the top of this page

HOME - NEWS - EVENTS - MARKETPLACE - CLASSIFIEDS - VISITOR INFO - CONTACT - PRIVACY POLICY   Get FirefoxGet Firefox



©2009 The Mountain Times. All rights reserved. Reproduction of advertising and design work strictly prohibited.
474 Industrial Park Drive / PO Box 1815 • Boone, North Carolina  28607 • Telephone 828.264.6397 • Fax 828.262.0282 • Classifieds 828.264.1881